Sitterly Road & Clifton Park Center Road Intersection Improvement Project

Share Sitterly Road & Clifton Park Center Road Intersection Improvement Project on Facebook Share Sitterly Road & Clifton Park Center Road Intersection Improvement Project on Twitter Share Sitterly Road & Clifton Park Center Road Intersection Improvement Project on Linkedin Email Sitterly Road & Clifton Park Center Road Intersection Improvement Project link

Sitterly Road & Clifton Park Center Road Intersection Improvement Project

Project Overview:
This project aims to enhance and transform the intersection at Sitterly Road and Clifton Park Center Road, improving safety and accessibility for all transportation users. Key goals include:

  • Improved sidewalk connectivity to support pedestrian safety.
  • Reduction of vehicle conflict points to enhance traffic flow and safety.

Planned Improvements:

  • Construction of new sidewalks along:
    • Sitterly Road from Crossing Boulevard to Clifton Park Center Road.
    • Clifton Park Center Road from Clifton Country Road to the future Bass Pro Shops driveway.
  • Single lane roundabout at the intersection of Clifton

Project Budget & Funding:

  • Total Budget: $4,313,000
  • Federal Grant Funding: $3,450,000

Project Status:

  • Completed: Survey and Right-of-Way (ROW) Mapping; Wetland Delineation; Infiltration Testing;Geotechnical Investigations
  • Currently in the Preliminary Design Phase.
  • Transition to the Final Design Phase is expected in March of 2026

Construction Timeline:

  • Tentative Start: Summer 2027

Sitterly Road & Clifton Park Center Road Intersection Improvement Project

Project Overview:
This project aims to enhance and transform the intersection at Sitterly Road and Clifton Park Center Road, improving safety and accessibility for all transportation users. Key goals include:

  • Improved sidewalk connectivity to support pedestrian safety.
  • Reduction of vehicle conflict points to enhance traffic flow and safety.

Planned Improvements:

  • Construction of new sidewalks along:
    • Sitterly Road from Crossing Boulevard to Clifton Park Center Road.
    • Clifton Park Center Road from Clifton Country Road to the future Bass Pro Shops driveway.
  • Single lane roundabout at the intersection of Clifton

Project Budget & Funding:

  • Total Budget: $4,313,000
  • Federal Grant Funding: $3,450,000

Project Status:

  • Completed: Survey and Right-of-Way (ROW) Mapping; Wetland Delineation; Infiltration Testing;Geotechnical Investigations
  • Currently in the Preliminary Design Phase.
  • Transition to the Final Design Phase is expected in March of 2026

Construction Timeline:

  • Tentative Start: Summer 2027
Page last updated: 19 Nov 2025, 04:39 PM