Intersection Safety Improvements Project, State Route 146 at Miller Road & Tanner Road Intersections

Share Intersection Safety Improvements Project, State Route 146 at Miller Road & Tanner Road Intersections on Facebook Share Intersection Safety Improvements Project, State Route 146 at Miller Road & Tanner Road Intersections on Twitter Share Intersection Safety Improvements Project, State Route 146 at Miller Road & Tanner Road Intersections on Linkedin Email Intersection Safety Improvements Project, State Route 146 at Miller Road & Tanner Road Intersections link

Project Overview

This project focuses on improving traffic flow and safety at two key intersections along Route 146:

  • RT146 at Miller Road & Tanner Road
  • RT146 at Waite Road

The primary objective is to develop a design report for constructing single-lane roundabouts at each intersection. These improvements aim to reduce delays for side street traffic and enhance overall safety for all roadway users.

Project Scope

  • Develop detailed plans, specifications, and estimates (PSE) for design alternatives.
  • Evaluate and recommend roundabout configurations to improve intersection performance and safety.

Project Funding

  • Total Funding: $500,000 (Design Only)

Project Timeline & Key Milestones

MilestoneStatus
Kickoff MeetingCompleted – July 2024
Survey Fieldwork & Geotechnical TestingCompleted – Fall 2024
Draft Design DocumentUnder Review – May 2025
Final PSE DeliveryScheduled – October 2025

Project Overview

This project focuses on improving traffic flow and safety at two key intersections along Route 146:

  • RT146 at Miller Road & Tanner Road
  • RT146 at Waite Road

The primary objective is to develop a design report for constructing single-lane roundabouts at each intersection. These improvements aim to reduce delays for side street traffic and enhance overall safety for all roadway users.

Project Scope

  • Develop detailed plans, specifications, and estimates (PSE) for design alternatives.
  • Evaluate and recommend roundabout configurations to improve intersection performance and safety.

Project Funding

  • Total Funding: $500,000 (Design Only)

Project Timeline & Key Milestones

MilestoneStatus
Kickoff MeetingCompleted – July 2024
Survey Fieldwork & Geotechnical TestingCompleted – Fall 2024
Draft Design DocumentUnder Review – May 2025
Final PSE DeliveryScheduled – October 2025